The landscaped areas of Durrat Al Bahrain, included the golf course will be irrigated by water from a seawater desalination plant to be constructed at resort. Treatment facilities will be located on the mainland away from the occupied areas of the resort.
Total project capacity is 36,000 CuMD, but it will be executed on three phases each is 12,000 CuM/D.
Although effluent water will be used for irrigation purposes, but it must have the quality of potable water, considering that future bottling water is planned to use this water. |