Khuff Gas Project
Project Completion Date: December - 2012Project Briefing:
Saudi Aramco wants to prevent hydrate formation primarily during startup of wellhead.
Client Requirements:
Client requested chemical injection skids per each wellhead to avoid hydrate formation.
AES Solution:
AES provided Methanol Injection Skids to be used to inject Methanol into Wellhead Piping Stream of Choke Valves in order to prevent hydrate formation primarily during startup.
Conclusion and Results:
AES designed, fabricated, tested and supplied 40 nos. Methanol Injection Skids with 517 barg (7500 psig)discharge pressure by using special tubing of SS in the discharge line of the API Dosing Pumps